How to install a cement drain !

Drain pipe is an important part of drainage engineering, but the drainage pipe is generally divided into: flat mouth reinforced concrete cement pipe, flexible tongue and groove reinforced concrete cement pipe, socket reinforced concrete pipe, F-type steel socket cement pipe, flat mouth ring interface Cement pipe, cement pipe, etc.

Drainage pipe is an important part of drainage engineering. Its quality directly affects the quality of the entire project and also affects the normal operation of the entire drainage system. However, the drainage pipe is generally divided into: flat mouth reinforced concrete cement pipe, flexible grooved reinforced concrete cement pipe, socket socket reinforced concrete cement pipe, F-shaped steel socket cement pipe, flat mouth ring joint cement pipe, and tongue and groove cement pipe.

Cement drainage pipe device method

1. It is necessary to check whether each department is normal before use. Confirm that each hose is connected reliably.

2. When using, strictly abide by the rules in the main parameters, avoid overloading, or continue to suppress after arriving at the trip, otherwise when the lifting height or lifting tonnage exceeds the rules, serious oil leakage will occur at the top of the cylinder.

3. If the amount of oil in the pump body is insufficient, the working oil (32 # hydraulic oil) must be added to the pump before it can work.

4. For the electric pump, please refer to the operation manual of the electric pump.

5. The center of gravity of the heavy object should be selected properly, the force point of the electric jack should be reasonably selected, and the bottom surface should be flat. At the same time, the soft and hard conditions on the ground should be considered, and the tough wood should be lined.

6. The electric jack should be used to support the heavy object in time after the heavy object is pushed in. It is forbidden to use the electric jack as a support.

Application method of cement drainage pipe

1. Measurement: Measure the center line according to the drawing, and the distance between the straight line and the curve is 10m and 5m, and calculate the groove depth and slope.

2. Excavation of trenches: The excavation of trenches is mainly mechanical, artificially assists the origin, slope repair, and pay attention to the 20-30 cm base.

3. Substrate treatment: arrange the debris in the trench, and level and compact the substrate to ensure that the base conforms to relevant rules.

4. Pipeline foundation: After the undisturbed soil has been rammed, we can lay the pipeline directly on it. If the foundation is not good, the foundation should be treated first.

5. Piping device: Select the appropriate pipe, perform seam treatment on the pipe, and arrange the nozzle, so that the hair is wet. When lowering the tube, keep the substrate clean. Then line up the pipeline and calibrate the centerline and elevation

6, anti-corrosion treatment: check the completed pipeline of the device to ensure that there is no problem with the post-processing of the pipe.

7. Pipe trench backfill: backfill the trench from both sides of the pipeline, pay attention to draining the water in the trench, and then backfill the soil with the soil in accordance with the rules, then compact the fill.